What is one of the key considerations when planning for existing utilities during construction?

Prepare for your Virginia Highway Heavy Exam with our batch 2 quiz. Access flashcards and multiple-choice questions, complete with hints and explanations, to boost your chances of passing. Start your journey to success now!

When planning for existing utilities during construction, a critical consideration is the potential for significant delays if these utilities are poorly managed. Utilities such as water, electricity, gas, and telecommunications are vital infrastructures that can be disrupted during construction activities. If the planning phase does not adequately address the location, condition, and management of these utilities, it can lead to unforeseen complications. For instance, damaging a utility line can halt construction, require emergency repairs, or necessitate rerouting of lines, all of which contribute to project delays. This can further affect the overall schedule and budget, emphasizing the importance of careful coordination and planning to mitigate such risks.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy